Streets:
-
Staff cleaned East & West Main Street
-
Staff has repaired a
number of street lights
-
Staff removed the speed bumps for
the winter
-
Staff repaired and replaced a number
of street and stop signs
-
Staff arranged for the street strip
painting of Silo Hill Road
Water:
-
As the :ale water has cooled staff
has discontinued the injection of coagulant
treatment at Well #3
-
The roughing filters are
being backwashed twice everyday and the DE filters are
being done once every other day
-
The large 500,000 gal water storage
tank was drained, inspected, cleaned and placed back
on line this month
-
Optimum Controls, Inc. checked and
repaired a number of the automatic control and
communication systems at the water treatment plant
this month
-
Delauter has completed the first
phase of the water and sewer replacement project on
South Seton Avenue
-
Water production and
consumption. We produced and purchased an
average of 362,765 gpd. We consumed an average
of 310,084 gpd.
-
The difference is
"Backwash Water" ...(14.5%). We purchased
988,600 gals. of water from MSM this month.
-
52.7% of this water
came from wells
-
8.8% of this
water came from Mt. St. Mary's
-
38.5% of this water
came from Rainbow Lake
Wastewater:
Trash:
Parks:
-
Staff has been
performing standard mowing & trimming
-
Staff has winterized the bathrooms
in Memorial Park
-
The Prefabricated
bathroom for Community Park has been delivered and
final connection is almost finished
-
Staff mulched around the playground
equipment in Memorial Park
Meetings
Attended:
-
10/04 South Seton Ave water &
sewer project progress meeting
-
10/10 Catoctin Land Trust - Related
to Mountain Lands
-
10/10 Fox & Associates -
Community Park Trails System
-
10/11 Emmitsburg After-School
Program Staff
-
10/13 Land Owner - Discuss Possible
Annexation
-
10/18 South Seton Ave Water &
Sewer Project Progress Meeting
-
10/26 Frederick County Planning
Dept. - Thurmont Region Comp Plan Update
-
10/27 State Staff Driving Safety
Seminar
-
10/27 Land Owner - Discuss Possible
Annexation
-
10/31 Emmitsburg Business &
Professional Association
List of prior months' Town Manager's reports |
|
|
|
|
|